Latest News

Dongola Pilot Project Contract Signature
The implementation of the Dongola Pilot Wind Farm has been awarded to Emergya Wind Technologies BV, a pioneer in the distributed wind ene

Sudan Wind Atlas and GIS applications Workshop
Sudan Wind Atlas and GIS applications Workshop on December 17, 2019.
Venu: Sudanse Electricity Transmission Company (SETCO)

Outcome 2 Activities Presentation Workshop
The workshop presents the final draft report of the project's outcome 2 studies which includes:
- Formulation of Sudan long-te

Sudan FiT NAMA Workshop
A presentation and validation workshop about "Renewable Energy Feed-in-Tariff as a Nationally Appropriate Mitigation Actions (NAMA)

Pilot Project Kick-off Meeting
The MWRIE/WEP contracted with the Lahmayer International for consultancy services for Dongola wind farm pilot project.
The kick-of

Contract for Outcome 2 Activities
The MWRIE/WEP contracted with Regional Center for Renewable Energy and Energy Efficiency (RCREEE) to conduct the project's outcome 2 stud

The 7th Meeting of the Project Board
At this meeting, project activities and performance ratio for each activity were presented during the year 2018. The year 2019 work plan

14th Project Technical Committee Meeting
During the 14th meeting, the Project Technical Committee PTC members discussed and recommended the following:
- Wind Energy Pr
Email: This email address is being protected from spambots. You need JavaScript enabled to view it.